5.5 Overhead absorption rates – ABC
In activity-based costing (ABC), the concept of overhead absorption rates is not typically used as it is in traditional absorption costing. Traditional absorption costing calculates a predetermined overhead rate based on a single cost driver, such as direct labor hours or machine hours, and applies it to allocate overhead costs to products or services.
In ABC, the focus is on identifying and understanding the activities that drive costs within an organization, rather than relying on a predetermined rate. ABC allocates costs to products or services based on their actual consumption of activities and resources. It involves identifying cost drivers specific to each activity and measuring the resources consumed by those activities.
Instead of using an overhead absorption rate, ABC uses a more detailed and specific approach to allocate overhead costs. The steps involved in allocating overhead costs in ABC include:
- Identifying activities: Activities that contribute to the production or delivery of products or services are identified.
- Determining cost drivers: For each activity, cost drivers are identified. These are the factors that cause the activity to occur and consume resources. Cost drivers can be different for each activity and may include metrics such as machine hours, labor hours, number of setups, or square footage utilized.
- Measuring activity consumption: The actual consumption of activities by products or services is measured. This can be done through direct observation, time studies, or other data collection methods.
- Allocating costs: Based on the consumption of activities by products or services, costs are allocated to them. The costs are distributed based on the proportionate usage of the identified cost drivers.
QUESTION ONE
Wangu Manufacturing Company Ltd. is located at the industrial area in Nairobi. The company uses four different machine groups, A, B, C and D in its manufacturing process.
The overhead costs budget for the year ending 31 December 2003 is as follows:
| Sh. ‘000’ | |
| Indirect wages Holiday pay and national insurance Supervision Machine maintenance (wages) Supplies Power Tooling costs Insurance of machinery Insurance of buildings Depreciation Rent and rates | 12,000 10,200 16,680 14,000 2,600 4,200 13,300 2,520 1,600 10,500 12,400 |
| 100,000 |
At present, overheads are absorbed into the cost of the company’s products by means of a single direct wages percentage of 70 percent. The company wishes to change to machine hour overhead absorption rate for each of its four different machine groups. The following data is available for each of the four machine groups:
| Machine groups | |||||
| A | B | C | D | Total | |
| Sh. ‘000’ | Sh. ‘000’ | Sh. ‘000’ | Sh. ‘000’ | Sh. ‘000’ | |
| Tooling costs Supervision Supplies Cost of machines  Machine maintenance hours Number of direct workers Total number of workers Floor space (square feet) Machine running hours Machine power rating (kilowatts) | 5,400 5,170 1,200 32,000  3,000 6 26 3,000 30 55,000 | 4,100 4,720 800 24,000  2,000 6 34 2,400 60 27,000 | 2,600 3,630 200 10,000  4,000 2 15 1,600 25 8,000 | 1,200 3,160 400 18,000  1,000 2 10 1,000 10 15,000 | 13,300 16,680 2,600 84,000  10,000 16 85 8,000 125 105,000 |
Required:
a.Machine hour overhead absorption rate for each of the four groups of machines.
b.The overhead cost to be absorbed by product XY123 if:
i)It utilizes the following time resources of the indicated machine groups:
Hours Machine group
8 Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â A
 3       B
  1                                        C
   4                                        D
ii)Direct labour cost is Sh. 22,000,000 and the direct wages percentage
Solution:
a)Computation of Overhead Absorption Rates per Machine Hour
| Overhead | Absorption basis | A Sh.’000’ | B Sh.’000’ | C Sh.’000’ | D Sh.’000’ | Total Sh.’000’ |
| Indirect wages | No. of indirect workers | 3,478 | 4,870 | 2,261 | 1,391 | 12,000 |
| Holiday pay & National Insurance | No. of workers (Total) | 3,210 | 4,080 | 1,800 | 1,200 | 10,200 |
| Supervision | Actual | 5,170 | 4,720 | 3,630 | 3,160 | 16,680 |
| Machine maintenance (wages) | Machine maintenance hours | 4,200 | 2,800 | 5,600 | 1,400 | 14,000 |
| Supplies | Actual | 1,200 | 800 | 200 | 400 | 2,600 |
| Power | Machine power | 2,200 | 1,080 | 320 | 600 | 4,200 |
| Tooling costs | Actual | 5,400 | 4,100 | 2,600 | 1,200 | 13,300 |
| Insurance – Machinery | Cost of machines | 960 | 720 | 300 | 540 | 2,520 |
| Insurance – buildings | Floor space | 600 | 480 | 320 | 200 | 1,600 |
| Depreciation | Cost of machines | 4,000 | 3,000 | 1,250 | 2,250 | 10,500 |
| Rent & rates | Floor space | 4,650 | 3,720 | 2,480 | 1,550 | 12,400 |
| Total | 34,978 | 30,370 | 20,761 | 13,891 | 100,000 | |
| Therefore No. of machine hours: | 30 | 60 | 25 | 10 | ||
| Absorption rate per machine hour | 1,165.93 | 506.17 | 830.44 | 1,389.1 | ||
b) Product XY 123
| (i) | Absorption rate | No. of Hours | Overhead Absorbed Sh.’000’ | ||
| A B C D | 1,165.93 Â Â 506.17 Â Â 830.44 1,389.10 | 8 3 1 4 | 9,327.44 1,518.51 830.44Â Â 5,556.40 | ||
| 17,232.79 |
(ii) Overhead:
= 70% of direct wages
                                     =        70% x 22,000,000 = 15,400,000